Measure the real constraint
Establish whether the limiting factor is contracted demand, transformer capacity, generator capacity, tariff exposure or inadequate operating visibility.
JME Energy & Automation engineers control strategies that coordinate grid import, BESS, solar PV, gensets and manageable loads to reduce demand peaks without compromising critical plant operations.
Demand management is not simply switching loads off. The control system must understand available capacity, tariff periods, battery state of charge, generator limits, process priorities and the duration of the expected peak.
Establish whether the limiting factor is contracted demand, transformer capacity, generator capacity, tariff exposure or inadequate operating visibility.
Choose the correct mix of BESS discharge, solar utilization, staged load control, generator support or operator notification.
Define how loads return, how battery reserve is restored and how the system behaves after utility, meter or communication failure.
JME connects meters, controllers and controllable assets through an EMS or PLC layer with transparent limits and operator visibility.
Discharge when measured import exceeds the agreed target, subject to PCS power, battery SOC, temperature and reserve requirements.
See JME’s real SolarEast 215 kWh BESS integration in Pakistan →
Coordinate charging and discharging around tariff windows where the commercial and technical operating strategy supports it.
Remove lower-priority loads in stages when available capacity is insufficient, then restore them using stable thresholds and delays.
Use available PV production while respecting zero-export, generator-loading and equipment limitations.
Start or load generators when the agreed operating philosophy requires additional capacity or resilience.
Provide alarms, recommended actions and demand forecasts where automatic control is unnecessary or operational approval is required.
| Input | Why it matters |
|---|---|
| Load profile | Shows the magnitude, frequency and duration of demand peaks. |
| Tariff and demand limits | Defines the commercial target and operating windows. |
| BESS capability | Confirms usable power, energy, SOC limits and supported PCS modes. |
| Generator limits | Protects minimum loading, reverse power, ramping and available capacity. |
| Load priorities | Separates critical, essential, deferrable and shed-capable loads. |
| Metering and communications | Determines response speed, accuracy and failure handling. |
It is the controlled reduction of a facility’s maximum electrical demand using battery discharge, generation, renewable energy or manageable loads.
It can support both demand reduction and backup objectives, but the control philosophy must preserve sufficient state of charge and respect PCS operating modes.
No. Peak shaving may use BESS or generation without interrupting loads. Load shedding intentionally disconnects selected loads when capacity is insufficient.
Yes, when the installed devices expose suitable measurements and commands through supported interfaces such as Modbus RTU, Modbus TCP, RS485 or Ethernet.
Performance should be checked using time-synchronized demand, source-power, battery, alarm and operating-mode trends against agreed acceptance criteria.
Share 12 months of utility bills, available 15- or 30-minute demand data, tariff information, SLD, BESS details, generator capacities and critical-load priorities for an initial engineering review.