Engineering documents
- Approved SLD and control philosophy
- Panel GA and wiring drawings
- I/O and communication point lists
- Equipment datasheets and settings
- Cause-and-effect or mode matrix
A practical framework for PLC, HMI, SCADA, EMS, synchronization, switchgear and hybrid-energy systems—so the delivered installation can be tested, understood and maintained.
Successful commissioning proves field wiring, measurements, logic, interlocks, communications, alarms, operator actions and failure responses. A dashboard that looks complete is not evidence that the underlying system is ready for operation.
Complete these checks before dispatch or site implementation where the project scope permits.
SAT verifies the installed system against real field equipment, electrical conditions and operating modes.
| Test area | Minimum verification | Required evidence |
|---|---|---|
| Field signals | End-to-end proving of digital and analogue inputs, outputs, CT/PT scaling and breaker feedback. | Signed point sheet and representative photographs. |
| Commands | Local/remote selection, start/stop, breaker operation and command rejection under unsafe conditions. | Command log and interlock results. |
| Operating modes | Grid, generator, solar, BESS, island, recovery and maintenance modes applicable to the project. | Mode test record with initial conditions and outcome. |
| Alarms and faults | Alarm creation, timestamp, acknowledgement, reset, history and escalation. | Alarm list and event screenshots. |
| Failure response | Communication loss, sensor failure, controller restart, power interruption and safe fallback. | Failure-injection record and recovery result. |
| Performance | Response time, synchronization conditions, load sharing, control stability and relevant power limits. | Trends, meter readings and acceptance criteria. |
FAT verifies the engineered panel, logic, screens and communications before site acceptance. SAT proves the installed system against real field wiring, equipment and operating conditions.
Yes. JME can provide an independent review, point verification, communication testing, logic assessment, punch-list development and staged recovery subject to access and available documentation.
At minimum: source measurements, operating modes, charge/discharge limits, generator loading constraints, export control, alarms, communications, failure response and operator actions.
Yes. Use the “Print / Save Checklist as PDF” button and select your browser’s PDF destination.
Share the available drawings, screenshots, controller details and problem statement. JME can review the system before FAT, SAT, handover or retrofit.