JME Engineering Guides · Solar buying checklist
How to Compare Solar Installation Quotes in Pakistan
Quick answer. Ask both installers to quote the same scope, then compare exact equipment models, estimated annual generation, installed price, warranties, and what is tested at handover. For a factory, get generator operation, export limits, and future battery plans written into the proposal.
Published by JME Energy & Automation ·
Put both quotes side by side
| Compare this | Ask both installers to specify |
|---|---|
| System size and equipment | Panel count, wattage, and exact panel and inverter model numbers. Compare total panel capacity in kWp DC separately from inverter output in kW AC. |
| Expected generation | Estimated first-year kWh and the assumptions for roof orientation, tilt, shading, and losses. Where export is limited, ask how the estimate accounts for restricted output. |
| Installed price and exclusions | Get an itemized bill of quantities and confirm taxes, mounting, cabling, protection, metering, civil work, and any utility paperwork. Ask who is responsible for anything excluded. |
| Backup and batteries | Confirm which circuits can run in an outage, usable battery energy in kWh, backup output in kW, and any equipment needed for transfer. Ask for the backup scope to be priced separately if you are comparing options. |
| Warranty and support | Separate panel product and performance warranties, inverter and battery coverage, and installation workmanship. Ask who handles claims and whether labour or transport is included. |
| Commissioning and handover | Get a written test list. Ask for the single-line diagram, equipment serial numbers, access to monitoring, warranty documents, and test records. |
| Factory operating modes | Ask what happens when WAPDA is available, when the generator takes over, and when site load drops. Confirm who supplies and tests metering, export control, and any plant controller or EMS. |
Example. Two quotes may both say “10 kW solar” while using the same 10 kWp of panels with different AC inverter ratings. Ask why each inverter was selected and what annual yield it is expected to deliver. If only one quote includes a backup distribution board, get the other installer to price that scope before comparing totals.
| Item | Quote A | Quote B |
|---|---|---|
| Panel capacity | 10 kWp DC | 10 kWp DC |
| Inverter output | 8 kW AC | 10 kW AC |
| Annual yield assumptions | Stated | Request in writing |
| Backup distribution board | Included | Request separate price |
Four things to confirm before you sign
- Ask for a site survey and a final equipment schedule.
- Make both installers price the same base scope, with optional batteries or backup listed separately.
- Get the generation assumptions, warranty responsibilities, exclusions, and commissioning tests in writing.
- For an industrial site, ask the installer to describe and demonstrate the agreed operating modes at handover.
Common questions
Should I compare the price per watt?
Use it as a quick check only after matching scope. Divide the comparable installed price by total panel watts, then review equipment, warranties, backup, and commissioning separately.
Is the annual generation estimate guaranteed?
Treat it as an estimate unless the contract expressly guarantees a result. Ask for the calculation assumptions and the terms of any guarantee in writing.
What is the difference between panel kWp and inverter kW?
Panel kWp is the combined rated DC capacity of the panels under standard test conditions. Inverter kW is the AC power rating. Ask for both numbers.
Does a hybrid inverter quote include backup for the whole property?
Ask which circuits will be backed up and what load the system can carry. Check battery capacity and any backup board or switching equipment included in the quote.
How do I compare two factory solar quotes if we already have generators?
Ask both installers for the same operating sequence on utility, generator, and transfer. Have them identify the meters, inverter controls, and tests included in their price.
Review the industrial operating scope with JME
JME Energy & Automation helps plant teams review how proposed solar will interact with existing generators, switchgear, batteries, and site export limits.